Crews are making steady progress and are now moving closer to the intersection of Tustin St. and Taft Ave. Once work is completed, they will move onto Tustin St. and continue heading north working towards Taft St. along the project route.
Current Work
Location: Taft Ave. from Cambridge St. to Tustin St.
What:Â Pipeline replacement work
When: Currently ongoing–Winter of 2025*
Hours: 8:30 a.m.—4 p.m., M–F
Construction continues with crews rehabbing the pipeline located in the median, which will take approximately three months. They will be working in sections from Cambridge St. and Tustin St. on Taft. Ave.Â
Project Impacts:
- Turn restrictions will be in place, please follow posted signs.
- Crosswalks may be closed intermittently, please follow posted signs.
- Bike lanes will be unavailable during this time.
- No street parking along the work area.
- At least one lane will remain open for east and westbound traffic.
- Bus stops along Taft Ave. will be impacted during construction. Visit www.octa.net for details.
- Increased activity, dust, and noise are expected near the construction zone.

We appreciate the community’s continued patience and cooperation as we complete this important infrastructure improvement.
*All dates and times are subject to change due to operational factors or inclement weather.
Project Description:Â
The Taft Avenue Sewer Improvement Project will replace and relocate a portion of the Taft Sewer in the City of Orange.
This project will upsize almost two miles of pipe along Taft Avenue from Glassell Street to Sacramento Street, northbound on Sacramento Street to Brentford Avenue, to Breckenridge Street to Meats Avenue. The current pipe ranges between 12 to 15 inches and will be upsized to 18 to 21 inches.
A portion of the sewer that currently runs along Tustin Street will be relocated to North Sacramento Street where there is more room to install a larger pipe and facilitates the future maintenance of the pipeline.
Project Schedule: December 2024 – Fall 2026
Local Sewer ProviderÂ
- City of Orange – Water Division – (714) 288-2475
Project Location
Stay In The Know
Community Liaison:
(714) 378-2965
Email:
constructionhotline@ocsan.gov
Sign up for text alerts:
click here
Signup for Email Notification
Site Location
Construction Schedule
2024 - 2026
Construction Budget
$20.4 million